October – December 2018

Carry out Site Investigation (Tung Ping Chau Public Pier)

August 2018 – August 2019

Carry out Ecological Impact Assessment

October 2018 – Mid-2020

Carry out Environmental Impact Assessment

April - July 2019

Carry out initial stakeholder consultation

July - September 2019

Carry out Site Investigation (Lai Chi Wo Pier)

August 2019 – May 2020

Carry out stakeholder consultation

October – November 2020

EIA Reports public inspection period

29 December 2020

EIA Reports were approved with conditions